FSU KELLUM HALL DEMOLITION
Project Location:
Tallahassee, Florida
Project Completed:
2016
Project Elements:
George & Associates was tasked with developing a demolition plan for all the civil utilities associated with Kellum Hall Dormitory and developing a site plan for the property after the demolition of the dormitory building. The site plan required the design of temporary ADA pedestrian access around the site as well as temporary traffic routes. Existing potable and fire, sewer, and gas lines required detailed plans for the safe removal of these utilities. The final site design required grading and drainage to control runoff and provide a stable and erosion-resistant site.